You are here: Operations » System Performance Data » Capacity Adequacy Indicator

Capacity Adequacy Indicator

Capacity Adequacy Indicator

The Capacity Adequacy Indicator is a method of assessing the ability of available generation to meet the predicted system demand.

We publish the results for capacity adequacy each Thursday.  These results contain the prediction for the following four weeks, commencing the following Sunday.  It is updated each Monday.

Below this table is a brief explanation of the results provided.

Date Expected CDGU & MW (If FOP = 0%) Expected Daily Peak Demand MW Expected Reserve at Peak MW (If FOP = 0%) Expected LOLH in Hours (for Committed Outage Programme)
06/02/2012 7440 4533 2907 0.0000
07/02/2012 7440 4533 2907 0.0000
08/02/2012 7440 4533 2907 0.0000
09/02/2012 7440 4533 2907 0.0000
10/02/2012 7440 4533 2907 0.0000
11/02/2012 7440 4123 3317 0.0000
12/02/2012 7440 3883 3557 0.0000
13/02/2012 7440 4473 2967 0.0000
14/02/2012 7355 4473 2882 0.0000
15/02/2012 7355 4473 2882 0.0000
16/02/2012 7355 4473 2882 0.0000
17/02/2012 7355 4473 2882 0.0000
18/02/2012 7355 4069 3286 0.0000
19/02/2012 7355 3832 3523 0.0000
20/02/2012 7265 4476 2789 0.0000
21/02/2012 7265 4476 2789 0.0000
22/02/2012 7265 4476 2789 0.0000
23/02/2012 7265 4476 2789 0.0000
24/02/2012 7265 4476 2789 0.0000
25/02/2012 7265 4071 3194 0.0000
26/02/2012 7265 3835 3430 0.0000
27/02/2012 7265 4389 2876 0.0000
28/02/2012 7265 4389 2876 0.0000
29/02/2012 7265 4389 2876 0.0000
01/03/2012 7355 4389 2966 0.0000
02/03/2012 6923 4389 2534 0.0000
03/03/2012 6923 3957 2966 0.0000
04/03/2012 7008 3734 3274 0.0000

Capacity Adequacy Indicator

Expected CDGU & Interconnector Availability

This is calculated as the sum of all Centrally Dispatched Generation Units (CDGUs) and the interconnector with Northern Ireland Electricity (NIE) that are expected to be available for a given peak, if the Forced Outage Probability (FOP) of all CDGUs and the interconnector = 0%.

Expected Daily Peak Demand

The Expected Daily Peak Demand displayed here represents the electricity production at the peak that is required to meet the national electrical consumption, including system losses and generators' requirements.  It includes consumption met by power imported via the interconnector, but excludes consumption met by some of the non-centrally monitored generation.

Expected Reserve at Peak

This is calculated as the difference between the "Expected CDGU & Interconnector Availability" and the "Expected Daily Peak Demand".  It should be noted that this reserve must be sufficient to cover any Forced Outages that may occur on the system, so as to ensure that the adequacy standards are not breached.

Expected Loss of Load Hours (LOLH) for the Committed Outage Program

This is the loss of load hours expected and is an indication of the likely duration over which the system demand may not be met.  The Generation Adequacy Standard is eight hours LOLH per year, which equates to 0.022 hours per day on average if the risk is evenly distributed over the year.

Centrally Dispatched Generation Unit (CDGU)

This refers to a Generation Unit that is normally subject to EirGrid's Dispatch Instructions.

Forced Outage Probability (FOP)

This is the forced outage probability - the probability, in percentage terms, that a generation unit will not be able to provide Energy or Ancillary Services.

Committed Outage Program

This is a program of outages of the Generator's power plant, prepared by EirGrid.

2012 Capacity Adequacy Indicator

2012 Capacity Adequacy Indicator can be found here